雙組份打膠機(jī)的操作流程
雙組份打膠機(jī)的操作過(guò)程十分的簡(jiǎn)單,小編大概總結(jié)下分為兩個(gè)部分一個(gè)是控制系統(tǒng)的操作,另一個(gè)就是膠桶的安裝/更換,具體點(diǎn)的方法如下。
The operation process of the double component glue machine is very simple. It is divided into two parts, one is the operation of the control system, the other is the installation / replacement of the buckets, and the specific point is as follows.
1.接通電源(380V 三相四線)和氣源(0.6-0.7MPa)。
1. connect the power supply (380V three-phase four lines) and gas source (0.6-0.7MPa).
2.打開(kāi)A,B膠供膠閥門(mén),關(guān)閉B膠回流閥門(mén)。
2. open A, B glue for glue valve, close B glue return valve.
3.在控制面板上選擇“開(kāi)機(jī)”然后檢查一下A,B膠是否工作正常。此時(shí)供膠機(jī)混膠工作準(zhǔn)備就緒。
3. select the "boot" on the control panel and check if the A B glue is working properly. The glue mixing machine is ready at this time.
4、如果長(zhǎng)時(shí)間不用(超過(guò)15分鐘)或者是下班時(shí)要在控制面板上選擇“沖槍”,然后打開(kāi)B膠回流閥門(mén),關(guān)閉B膠供膠閥門(mén).此時(shí)供膠機(jī)沖槍準(zhǔn)備工作就緒。
4. If you do not use (more than 15 minutes) for a long time or at the end of the day, select the "gun" on the control panel, then open the B glue reflux valve and turn off the B glue valve.
5、每次操作前確保設(shè)備的水平度,調(diào)整機(jī)器的水平度,調(diào)節(jié)地腳的高度使機(jī)身水平。
5, ensure the level of equipment before each operation, adjust the level of the machine, adjust the height of the foot to make the fuselage level.
6、接通電源后先檢查各電機(jī)的旋轉(zhuǎn)方向是否正確,接通與CL—A—01打膠機(jī)的膠管,信號(hào)。
6, after switching on the power supply, check whether the rotation direction of the motors is correct, and connect the hose with the CL - A - 01 gluing machine.
感謝大家在百忙之中關(guān)注公司發(fā)布的產(chǎn)品信息,如果你想要了解更多,可以來(lái)我們公司咨詢。我們歡迎大家的光臨,并與你的合作!
Thank you for your busy schedule to pay attention to the product information released by the company. If you want to know more, you can come to our company for consultation. We welcome your presence and cooperate with you!
上一篇:中空玻璃打膠機(jī)都有哪些作用呢
下一篇:雙組份打膠機(jī)的操作你了解嗎?