雙組份打膠機(jī)安裝的幾點(diǎn)正確順序
雙組份打膠機(jī)是生產(chǎn)中空、幕墻玻璃的專用設(shè)備,可一次完成二道密封中A、B組份混合與涂膠。適用配比精度高的膠種,滿足玻璃深加工企業(yè)率、高合格率流水線作業(yè)的生產(chǎn)需求,那么雙組份打膠機(jī)安裝的順序是怎樣的?一起來(lái)看一下吧。
The two-component gluing machine is a special equipment for the production of hollow and curtain wall glass, which can complete the mixing and gluing of components a and B in the secondary sealing at one time. It is applicable to the glue with high matching accuracy and meets the production requirements of high-efficiency and high pass rate assembly line operation of glass deep processing enterprises. What is the installation sequence of the two-component gluing machine? Let's have a look.
1、雙組份打膠機(jī)設(shè)備應(yīng)安裝在干燥、無(wú)粉塵、無(wú)腐蝕性氣體的壞境中(該要求與其他設(shè)備一致,當(dāng)然如果條件達(dá)不到少爭(zhēng)取無(wú)腐蝕性氣體,畢竟設(shè)備中有電線以及管路這些配件抗腐蝕性不高)。
1. The two-component glue applicator equipment shall be installed in a dry, dust-free and corrosive gas free environment (this requirement is the same as that of other equipment. Of course, if the conditions are not met, at least strive for non corrosive gas. After all, the equipment has wires and pipes, and these accessories have low corrosion resistance).
2、室內(nèi)溫度更好控制在10~40度的室內(nèi)堅(jiān)硬地面上,地面應(yīng)水平度要好。(小編這里說(shuō)的地面水平度要好不一定要非常的平整才行,我們的設(shè)備在設(shè)計(jì)之初已經(jīng)考慮到了地面復(fù)雜性的因素所以對(duì)地面平整度是有相當(dāng)大的忍讓度的,只要不是幅度提別的大一般都可以正常工作。)
2. The indoor temperature should be better controlled on the indoor hard ground of 10-40 degrees, and the ground should be level. (the ground levelness mentioned by the editor here does not have to be very flat. At the beginning of the design, our equipment has taken into account the complexity of the ground, so it has a great tolerance for the ground levelness. As long as the range is not increased, it can generally work normally.)
3、雙組份打膠機(jī)安裝之前,應(yīng)先檢查是否有因運(yùn)輸、搬動(dòng)造成的變形、損壞和緊固件松動(dòng)情況,之前就曾經(jīng)有客戶在移動(dòng)打膠機(jī)的過(guò)程中把設(shè)備的智能控制系統(tǒng)的一個(gè)零部件碰掉了而導(dǎo)致設(shè)備無(wú)法正常運(yùn)行,我們的工作人員到現(xiàn)場(chǎng)后才排查出的原因。
3. Before the installation of the two-component glue applicator, it is necessary to check whether there is deformation, damage and looseness of fasteners caused by transportation and moving. Previously, a customer knocked off a part of the intelligent control system of the equipment during the process of moving the glue applicator, which caused the equipment to fail to operate normally. Our staff found out the reason after arriving at the site.
4、我們可以根據(jù)地面平整度的實(shí)際情況來(lái)通過(guò)調(diào)整設(shè)備的可升降地腳螺栓來(lái)調(diào)整設(shè)備的水平度直到設(shè)備水平而穩(wěn)固。然后按圖接線并可靠接地,把氣源接入機(jī)器所配帶的氣源接口,確保無(wú)漏氣現(xiàn)象。
4. First, we can adjust the levelness of the equipment by adjusting the lifting anchor bolts of the equipment according to the actual situation of the ground flatness until the equipment is horizontal and stable. Then connect the wires according to the drawing and reliably connect the air source to the air source interface provided by the machine to ensure no air leakage.
5、向油槽中加注液壓油指定位置,46#液壓油(約為50升左右)。
5. Fill the oil tank with hydraulic oil to the specified position, 46 # hydraulic oil (about 50L).
6、接通電源并打開(kāi)查看設(shè)備是否能夠正常運(yùn)行。
6. Turn on the power and check whether the equipment can operate normally.
The correct installation sequence of the two-component gluing machine is the above six aspects. If you have any questions about this, please come to our website at any time http://www.cztaiyue.com Consult and understand!