廠家與您分析雙組份打膠機(jī)重要的兩個(gè)部分的操作!
雙組份打膠機(jī)的操作過程非常簡單。它可以分為兩個(gè)部分。一是控制系統(tǒng)的操作,二是膠筒的安裝/更換。具體方法如下。
The operation process of the two-component gluer is very simple. It can be divided into two parts. One is the operation of the control system, and the other is the installation / replacement of the rubber cylinder. The specific methods are as follows.
①控制系統(tǒng)的操作方法
① Operation method of control system
1.連接電源(380V三相四線)和氣源(0.6-0.7mpa)。
1. Connect the power supply (380V three-phase four wire) and air source (0.6-0.7mpa).
2.打開a、B膠供膠閥,關(guān)閉B膠回膠閥。
2. Open the glue supply valves of a and B, and close the glue return valve of B.
3.在控制面板上選擇“上電”,檢查膠水a(chǎn)、B是否工作正常。這時(shí),給膠機(jī)的攪拌工作就做好了。
3. Select "power on" on the control panel to check whether glue a and B work normally. At this time, the mixing work of the glue feeder is completed.
4.如果長時(shí)間不使用(超過15分鐘)或下班時(shí)不使用,應(yīng)選擇控制面板上的“沖洗槍”,打開B回膠閥,關(guān)閉B供膠閥。這時(shí)給膠機(jī)的沖洗槍準(zhǔn)備好了。
4. If it is not used for a long time (more than 15 minutes) or after work, select the "flushing gun" on the control panel, open the B glue return valve and close the B glue supply valve. At this time, the washing gun of the glue feeder is ready.
5.每次操作前,確保設(shè)備水平度,調(diào)整機(jī)器水平度,調(diào)整基礎(chǔ)高度,使機(jī)身水平。
5. Before each operation, ensure the levelness of the equipment, adjust the levelness of the machine, and adjust the foundation height to make the fuselage level.
6.接通電源后,檢查各電機(jī)的旋轉(zhuǎn)方向是否正確,連接好cla-01打膠機(jī)的軟管和信號(hào)。(注:起膠齒輪泵電機(jī)的旋轉(zhuǎn)方向須與齒輪泵的旋轉(zhuǎn)方向一致)
6. After the power is turned on, check whether the rotation direction of each motor is correct, and connect the hose and signal of cla-01 glue applicator( Note: the rotation direction of the gluing gear pump motor must be consistent with the rotation direction of the gear pump)
②安裝/更換膠筒
② Install / replace rubber cartridge
②安裝/更換膠筒
② Install / replace rubber cartridge
1.在控制面板上選擇“AB膠壓板”。
1. Select "ab adhesive pressing plate" on the control panel.
2.然后選擇“上膠”,上膠壓力板就會(huì)上升。
2. Then select "glue", and the glue pressure plate will rise.
3.高度就位后,在控制面板上選擇“agluestop”
3. After the height is in place, select "agluestop" on the control panel
4.把壓盤下一個(gè)橡膠桶,打開蓋子的桶,解決內(nèi)心的塑料袋,并使上層的橡皮滾筒與壓盤(注意:對(duì)于新機(jī)器或新更換密封圈,外套橡膠表面的密封圈,以起到潤滑作用)。
4. Place the pressure plate next to the rubber bucket, open the bucket with the cover, solve the inner plastic bag, and connect the upper rubber drum with the pressure plate (Note: for a new machine or a new replacement of the sealing ring, first coat the sealing ring on the rubber surface for lubrication).
5.打開膠水a(chǎn)壓板上的排氣閥,然后選擇“膠水a(chǎn)滴”。這時(shí),壓板上的a膠會(huì)下降。當(dāng)壓板即將落桶口時(shí),停止下落。檢查壓板是否對(duì)準(zhǔn)槍管口,調(diào)整槍管位置直對(duì)準(zhǔn)。
5. Open the vent valve on the glue a pressing plate and select "glue a drop". At this time, the a glue on the pressing plate will drop. When the pressing plate is about to fall to the barrel mouth, stop falling. Check whether the pressing plate is aligned with the nozzle of the gun barrel, and adjust the position of the gun barrel until it is aligned.
6.讓壓板間歇滴膠(即滴膠→停膠→滴膠-)。當(dāng)壓板壓入桶內(nèi)時(shí),可使壓板連續(xù)下降。此時(shí),空氣從排氣閥排出。當(dāng)膠水從排氣閥連續(xù)排出而無空氣排出時(shí),壓板停止下降,閥門關(guān)閉。
6. Let the pressing plate drip glue intermittently (i.e. drip glue → stop glue → drip glue -). When the pressing plate is pressed into the barrel, the pressing plate can be continuously lowered. At this time, air is discharged from the exhaust valve. When the glue is continuously discharged from the exhaust valve without air, the pressing plate stops falling and the valve is closed.
7.此時(shí)a管安裝已完成,工作準(zhǔn)備就緒。B膠筒的安裝方法與a膠筒相同。
7. At this time, the installation of a pipe has been completed and the work is ready. The installation method of B rubber cylinder is the same as that of a rubber cylinder.